MSKVY 1.0 & 2.0
Solar & Transmission Infrastructure

MSKVY 1.0 & 2.0

Sarvadnya Energies Portfolio

Overview

Project Mission

The MSKVY project focused on large-scale solar integration through advanced transmission infrastructure. Sarvadnya Energies served as a Transmission Contractor and Liaisoning Consultant, ensuring seamless execution across Nashik, Sinnar, and Dindori.

Scope of Work

42 MW solar project liaisoning and execution coordination
Development of 50+ km transmission line network with ROW clearances
Substation bay feeder erection and integration
Complete execution of pole erection, conductor stringing, and line integration
Testing, commissioning, and system synchronization support
Coordination with authorities for approvals and compliance

Execution Approach

1

Site survey & route finalization

2

Design & engineering (Transmission)

3

Foundation & pole erection

4

Hardware installation & conductor stringing

5

Statutory approvals & electricity board coordination

6

Energization approval & handover

Developer

Torrent Power

Location

Nashik, Sinnar, Malegaon, Dindori

Capacity

42 MW

Scope

Transmission & Liaisoning

Timeline

24 Weeks

Status

Project Fully Commisioned & Verified

Engineering Deep-Dive

Technical Analysis

Site Constraints

  • Major Right of Way (ROW) challenges across social and infrastructure corridors

  • Multiple government approvals (NHAI, BPCL, HPCL, Forest, PWD, HAL, MES)

  • Execution across hilly terrain and low-mobility areas

  • Limited accessibility for material and equipment movement

Technical Challenges

  • Electrical system complexity and integration

  • Grid connectivity and synchronization requirements

  • Execution under tight project timelines

  • Material and supply chain coordination

  • Environmental and weather-related challenges

  • Performance optimization across transmission network

Scale & Complexity

  • Alignment with structured government program guidelines

  • Coordination across contractors, authorities, and multiple teams

  • Handling 33kV / 11kV electrical systems

  • Integration with existing infrastructure

  • Parallel execution across multiple sites

  • Time-sensitive deployment within defined schedule

Compliance Considerations

  • Regulatory approvals and statutory clearances

  • Compliance with electrical standards and safety norms

  • Inspection and certification processes

  • Documentation and reporting requirements

  • Grid and utility compliance for system integration

Execution Results

Impact & Delivery

Evidence of Success

Project Impact

Our execution methodology is designed to create measurable value for stakeholders, the community, and the national energy infrastructure.

Successfully supported 42 MW solar project liaisoning

Facilitated 50+ km transmission line network

Achieved compliance with NHAI, BPCL, Forest, PWD, and HAL

Delivered execution within a 24-week timeline despite hilly terrain